  • Applications for which a permit has not been issued within one hundred eighty (180) calendar days following the date of application submission shall expire by limitation, and plans and other data submitted for review may thereafter be returned to the applicant or destroyed by the Building Official. The Building Official may extend the time for request by the applicant showing that circumstances beyond the control of the applicant have prevented action from being taken on the application. This request must be in writing to the Building Official prior to expiration of the application. No application shall be extended more than once. No extension shall exceed one hundred eighty (180) calendar days. In order to renew action on the application after expiration, the applicant shall resubmit plans and pay a new plan checking fee.

(Ord. 3462-C.S., § 1, effective 1-3-08)