§ 9-1.903. Temporary Occupancy.  


Latest version.
  • If any building or structure, including Groups R3 or U occupancy, is to be occupied with the approval of the Building Official prior to the final inspection and/or final corrections, the occupant, owner, and contractor shall sign a Temporary Certificate of Occupancy prior to occupying the building agreeing to make all corrections required and/or listed within thirty (30) calendar days of occupancy. If corrections are not completed within thirty (30) calendar days, the Building Official shall have the authority to request the immediate discontinuance of the electrical service and/or the gas service by the appropriate utility and may file a notice of noncompliance with the County Recorder. The notice of noncompliance shall be removed by the Building Official only after all items requiring correction are completed.

(Ord. 3465-C.S., § 1, effective 1-3-08)