§ 7-2.22. Notice of Completion of Backfill.  


Latest version.
  • Except in the case of a major project, upon completion of the backfill, permittee shall notify the Director of such completion. Utility companies which are authorized by the Director to do their own paving are not required to give such notice.

    The Director, upon receipt of such notice and upon inspection and approval of work, shall cause street cuts, not in the category of major projects, to be paved.

(Added by Ord. 3196-C.S., § 2, effective 2-1-01)