§ 5-6.905. Conditions for Transfers Other Than to City.  


Latest version.
  • A Transfer of Allocated Capacity is subject to the following additional process and conditions:

    (a)

    At least thirty (30) days prior to a proposed Transfer, an Industrial User shall provide the City with notice of its intent to do so by submitting an application for the proposed Transfer.

    (b)

    The City will review the notice and application to determine if the conditions for the Transfer are met within thirty (30) days.

    (c)

    If the City denies a Transfer of Allocated Capacity subject to this section because the then-existing wastewater infrastructure located on the property receiving the additional Allocated Capacity is not sufficient for the resulting wastewater discharge, the Transfer will be allowed if the proposed transferor or transferee makes provisions to correct any infrastructure deficiencies with improvements or operational modifications as may be needed to accommodate the additional wastewater proposed to be discharged from the property.

    (d)

    The City may initiate a Transfer subject to this section by written request, avoiding (a) and (b) above.

    (e)

    The City shall charge a legally compliant application review and processing fee in an amount to be set by the City to recover associated costs.

(Ord. 3655-C.S., § 1, effective 11-11-16)