§ 5-6.506. Drawing Submittal Requirements.  


Latest version.
  • (a)

    Detailed plans shall be submitted to the City for review of existing or proposed construction of pretreatment facilities, spill containment facilities, monitoring facilities, metering facilities, and operating procedures. City approval shall be received prior to commencement of construction. The review of the plans and procedures shall in no way relieve the user of the responsibility of modifying the facilities or procedures in the future, as necessary, to meet the requirements of this chapter or any requirements of other regulatory agencies.

    (b)

    All drawings shall include:

    (1)

    North arrow;

    (2)

    Scale size;

    (3)

    User name and address;

    (4)

    Drawing name and drawing number;

    (5)

    Date drawn or revised;

    (6)

    Name of draftsman and name of person approving drawing.

    (c)

    The City may require drawings to scale depicting the manufacturing process (waste generating sources), spill containment, pretreatment facilities, and/or monitoring/metering facilities.

    (d)

    The City may require a schematic drawing of the pretreatment facilities.

    (e)

    The City may require the drawings be prepared by a California registered chemical, mechanical, or Civil Engineer.