§ 10-2.116. Construction, Start of.  


Latest version.
  • Construction shall be started when all of the following have been completed by the developer:

    (a)

    Filing of full sets of building plans with the Chief Building Official and issuance of a building permit including electrical, plumbing, and mechanical permits.

    (b)

    Performance of all conditions of approval specifying "prior to the issuance of a building permit" as found in any applicable resolutions adopted by the Council, Commission, or Board.

    (c)

    Payment of all required fees, including building permit fees, and the posting and acceptance of all public improvement securities, if applicable.

    (d)

    Compliance with any environmental review procedures of the City.